Sir William Fry Reserve / Gas Works

Last updated: 1 October 2026

Sir William Fry Reserve (SWFR) is being redesigned by the Suburban Rail Loop Authority (SRLA) and its contractor Suburban Connect (SC). The HPA is represented along with other community organisations at quarterly meetings of the SRL Precinct Reference Group (PRG), the most recent on 17 September 2026.

Project Overview:

Location: The planned Cheltenham SRL station (to eventually be renamed) will be on and under SWFR, facing Southland Shopping Centre. A bus transfer station will have entry/exit from Bay Road.

Future Plans: Of the total 8.5 hectares of SWFR, 1.14ha will be taken by the station and approximately 2.5 ha for residential or commercial towers up to 60 metres (17-18 storeys) and an access road from Nepean Highway. During construction until 2035-6, about half of SWFR will be closed, after which some will be returned for public access. No acoustic shed or roof is planned over the work site.

Public Space Obligations: The SRLA is required to offset existing public space permanently lost with ‘new open space of a similar size and quality’. SRLA plans for SWFR are available online. Or you can read the HPA September 2025 submission HERE.

Offset Public Space: New public space commitments have to date been limited to 1.14ha in the former gasworks site for a 20m pedestrian and cycle corridor along the Frankston rail line, a pocket park adjoining Station Street and an activity lawn west of Remington Drive.

Gasworks Site: The 1.14ha offset was transferred from Development Victoria (DV) to the SRLA in mid 2026. The remaining 5ha under DV control is earmarked for future housing ranging in height from 43 to 52m (12 to 15 storeys) under the SRLA Structure Plan. The previous commitment that 11.6% of that site will be allocated to public open space was reconfirmed by the SRLA in July 2026.

Park Enhancements and Amenities: The SRLA is currently enhancing the northern half of SWFR including a larger skate park, full size basketball and futsal court, pickleball court, new public toilets and off leash dog area.

Timing: In June 2026, it was announced that works in Highett had been rescheduled more than 12 months earlier so the rail corridor between Highett and Heatherton can be utilised for testing.

Tree Clearance: Approximately 300 trees are to be removed from SWFR with ninety new ones planted. The tree clearance was to have been largely completed by the end of 2026. It has been postponed to 2027, along with initial excavation at the southern end of the park. This follows deferral of the awarding of station contracts until after completion of a technical review requested by Premier Carroll.

Updates

Gallery

Caption: Station Street Park (design)

Source: PRG June 2026

Caption: Sir William Fry Reserve aerial overview

Source: City of Kingston, October 2026

Caption: New skatepark (design)

Source: PRG June 2026

Caption: SRL station early 2026

Source: PRG June 2026