Highett Level Crossing Removal Project
Last updated: 1 October 2026
Responsible entity: Victorian Infrastructure Delivery Authority (VIDA)
Project Overview
The level crossings at Highett Road and Wickham Road are planned to be removed by an elevated line or “Skyrail”. A new Highett station with public open space and possible parking under the rail bridge is planned as part of the level crossing removal works. The Highett level crossings are being removed to improve safety and reduce traffic congestion. The boom gates at Highett are down for up to 50 minutes in the peak period of 7am to 9am. Significant residential development in Highett will increase congestion around the level crossings.
Project Status
To be delivered by 2033.
Project Background
October 2022: The Victorian Government committed to removing the level crossings at Highett Road and Wickham Road by 2029 by elevating the rail line and building a new Highett Station.
June 2024: The City of Kingston released some discussion designs for consideration. More details of these ideas can be found at https://www.yourkingstonyoursay.com.au/highett
May 2026: The Victoria Government revised the timeline for removal to 2032, to align with Suburban Rail Loop works
August 2026: The Victorian Premier announced the removal project to be pushed back to 2033, to reallocate $112 million in budget savings to help fund to road and pothole repairs across Victoria.
Critical Project Outcomes
The HPA encourages the State Government to engage with the Highett Community and Councils (City of Kingston and Baysde City Council) to develop a design that will produce a more connected and liveable Highett. Specifically, the HPA would like the community to have input on:
The design and use of open space
Shared user paths
East/West Connection points, including between Lyle Anderson Reserve and the proposed new linear park (Gasworks)
Bus stop locations
Enhanced road connectivity i.e. Graham Road/Railway Parade